Leaders in Life Sciences Representative Projects

Large-Scale Fit-Out - Global CDMO and Biosimilar Developer

The Challenge: Complex Designs and Rapid U.S. Expansion

As this company’s debut U.S. facility, the project functioned in many ways as a greenfield startup. The team was tasked with executing a fast-tracked build based on an inherited design, leading to significant gaps between initial plans and constructability.

Spatial density was a primary obstacle. The layout required fitting Grade A through D cleanrooms, gowning areas, clean storage, CGMP warehousing, and high-security process utilities into a highly compact footprint. Upper-level roof utilities and MEP systems were extremely crowded, demanding meticulous execution to prevent field conflicts.

Navigating changing client expectations and alignment gaps between the original design firm and facility operations further compounded project fluidness.

Construction Management: Bridging Design to Reality

Because Genesis did not author the original design, the construction management team stepped in to establish control, drive alignment, and protect project momentum.

  • Advanced BIM Modeling: Executed a five-month Building Information Modeling (BIM) coordination effort to map dense utility corridors and prevent spatial overlaps on the roof and above cleanroom ceilings.

  • Rigorous Change Control: Successfully processed and managed over 200 drawing revisions, 600+ Potential Change Orders (PCOs), and 430 Requests for Information (RFIs) to finalize design details without halting work on site.

  • Unified Field Execution: Integrated construction teams directly with commissioning personnel early in the schedule, maintaining steady progress despite shifting client requirements.

CQV & Asset Management: Driving Compliance and Phased Delivery

Stepping in as a trusted advisor for a client navigating U.S. regulatory frameworks for the first time, the CQV and Asset Management teams provided critical structure and leadership.

  • Quality Ecosystem Development: Guided the client in building compliant site procedures, workflows, and operational documentation from the ground up.

  • Agile Phased Release: Adapted to unforeseen mechanical equipment delays by executing interim qualification releases for primary process suites, allowing client business operations to move forward without waiting for full-facility handover.

  • Scope Expansion: Delivered high-level leadership and clear scheduling priorities, leading directly to Genesis being awarded the complete qualification scope for the facility.

Key Takeaways

Despite inherited design hurdles, intense spatial limits, and tight timelines, Genesis delivered a fully functional, highly compliant 41,000 SF manufacturing center. Through close cross-functional collaboration across CM, AMS, and CQV, the team brought order to a complex environment and successfully launched our client’s U.S. manufacturing presence.